24 x 7 World News

How Japan is looking deep underground to solve its carbon problem

0

Home to numerous factories, refineries and thermal power plants, Chiba bears the dubious distinction of emitting the most carbon dioxide out of JapanтАЩs 47 prefectures.

One possible solution as the country pushes toward its carbon neutrality goal? A long pipeline stretching across the prefecture, which would transport captured CO2 so it can be buried offshore 1,000 to 3,000 meters below the seabed.

ThatтАЩs the vision of a public-private initiative that aims to capture 2% of the prefectureтАЩs emissions, based on 2021 levels, by 2030 тАФ and potentially more in the future.

The Chiba project is just one of nine тАЬadvancedтАЭ carbon capture and storage (CCS) projects that the government-owned Japan Organization for Metals and Energy Security (JOGMEC) selected in July 2024 in order to evaluate the feasibility of CCS in JapanтАЩs energy transition, all with an eye to commercialization by 2030. If given the go-ahead through a final investment decision planned for the fiscal year beginning April 2026, five of the projects will store captured CO2 domestically, with the remaining four sending it overseas.

The government and industry hope CCS will allow CO2-generating activities that are seen as economically vital to continue operating тАФ at least to some extent as they have done тАФ even as the country works to achieve net-zero emissions by 2050. And the government is investing billions of yen to get CCS off the ground: In fiscal 2023 and 2024, the total budgets for JOGMECтАЩs advanced CCS projects were ┬е23.9 billion (roughly $152 million at current exchange rates) and ┬е33.2 billion, respectively.

But the technology isnтАЩt without controversy. Some critics тАФ citing high costs and lingering uncertainties тАФ say CCS should only play a minimal, niche role in the energy transition. In particular, CCS should not be used as a lifeline for the fossil fuels driving climate change, they argue.

тАЬIf it doesnтАЩt work out, it will have an enormous impact on whether Japan can meet its emission reduction targets,тАЭ cautions Ayumi Fukakusa, deputy executive director of the nonprofit Friends of the Earth (FOE) Japan.

Major expense or major potential?

Contrary to its contemporary image as a potential climate solution, capturing carbon and injecting it underground wasnтАЩt actually invented as a countermeasure against warming. In fact, it was pioneered in the 1970s by the oil and gas industry, which sought to repurpose CO2 for a process called тАЬenhanced recoveryтАЭ in order to boost extraction.

Today, 73% of the worldтАЩs current carbon capture capacity is used for this purpose, according to the Institute for Energy Economics and Financial Analysis (IEEFA). The Global CCS Institute reports that a total of 50 CCS projects were operating worldwide in 2024, boasting a capture capacity of 51 million metric tons of CO2 тАФ just 5% of the annual 1 billion metric tons of CO2 that should be captured and stored in the International Energy AgencyтАЩs тАЬnet-zero emissions by 2050 scenario.тАЭ

Still, the Ministry of Economy, Trade and Industry, which leads JapanтАЩs energy plans, positions CCS as тАЬindispensable for decarbonizing thermal power plants,тАЭ and says that it should be тАЬfully utilizedтАЭ in high-emitting sectors like steel and chemical manufacturing.

Bloomberg

According to the governmentтАЩs CCS roadmap, Japan aims to annually store an estimated 120 million to 240 million tons of CO2 by 2050, the high end of which would require establishing roughly 480 injection wells, at an estimated cost of ┬е5 billion or ┬е8 billion per well depending on whether it is on or offshore.

The five JOGMEC-supported projects that plan to store CO2 off JapanтАЩs coasts are near Hokkaido, western Tohoku, Niigata Prefecture, western Kyushu and Chiba. Most intend to inject the CO2 into saline aquifers тАФ a type of underground rock formation thought to have the largest capacity and greatest safety for CO2 storage тАФ while the Niigata site targets an oil and gas field.

The Hokkaido-based project is actually a continuation of an existing CCS initiative, supported by the governmentтАЩs New Energy and Industrial Technology Development Organization, in the port city of Tomakomai. From 2016 to 2019, the pilot facility тАФ which cost approximately ┬е30 billion to construct тАФ captured roughly 300,000 tons of CO2 and injected it about 1,000 meters below the nearby seabed. Operators have been monitoring the site for seepage, an issue that has impacted CCS projects overseas, and seismic activity since then. So far, so good, they say.

Naturally, thorough monitoring doesnтАЩt come cheap. At Tomakomai, operators installed expensive equipment on the ocean floor to receive real-time data, explains Hiroshi Nambo, the Global CCS InstituteтАЩs Japan branch representative.

тАЬMonitoring is important, but … the cost of monitoring should be minimized,тАЭ he says.

A JOGMEC spokesperson echoes that sentiment, noting that the method, frequency and duration of monitoring across the nine exploratory projects will depend on both regulatory requirements and cost-effectiveness. Monitoring plans тАФ still under consideration тАФ may therefore differ by project and by site, the spokesperson explains.

Although JapanтАЩs new CCS Business Act does require monitoring, including after CO2 injection finishes, it does not specify minimum monitoring requirements.

Alongside further assessment of potential storage sites, clarifying CCSтАЩs costs is a major goal of the exploratory projects.

тАЬThe capture technology is ready and emission sources are ready,тАЭ Nambo says. тАЬThe problem is economics: how the project proponents prepare that investment and how to justify the economics for the total operation period.тАЭ

In a 2024 report, the Oil and Gas Climate Initiative, an industry-led organization, assessed that Japan has 152.27 gigatons of CO2 storage capacity, but so far none of that has been judged economical to access.

тАЬGovernment financial support is absolutely necessaryтАЭ at this stage, Nambo says.

In a December government estimate of electricity costs in 2040, power generated at CCS-equipped gas and coal power plants was more expensive compared with all renewables (aside from small-scale hydropower and controversial biomass). If deployed, CCSтАЩs high costs will likely be shouldered by residents, whether through increased electricity bills or higher public spending, critics say.

Keep it in the ground

Carbon capture technologies target CO2 generated at various points in the combustion process or capture it directly from the air. The JOGMEC-supported projects all plan to use the former, a comparatively easier approach, capturing carbon from specific facilities.

Still, the rate of carbon actually captured by that CCS technology is another point of contention between proponents and critics.

Roughly 95% тАФ or even close to 100% тАФ of CO2 passed through a capture plant can be secured, says Alex Zapantis, a strategic adviser with the Global CCS Institute.

тАЬNot all of the CO2 from a facility is passing through the capture plant in most places,тАЭ Zapantis explains. тАЬUltimately, itтАЩs an economic decisionтАЭ as to how much CO2 an operator will aim to capture, he says, noting that market demand is now dictating capture rates as close to 100% as possible.

However, IEEFA analysts highlight that, based on available data, CCS projects to date have only captured a maximum of roughly 80% of the CO2 passed through the capture technology. In many cases, that percentage is much lower.

тАЬUnfortunately, most of the existing carbon capture facilities do not publish … their actual CO2 capture rates,тАЭ a 2023 IEEFA report noted.

Japan Times

For the nine CCS projects selected by JOGMEC, тАЬno target is set for the recovery rate for the total CO2 emissions of the facilities subject to CO2 capture. Targets are being considered based on what is reasonable for each facility, including their technical and business aspects,тАЭ the JOGMEC spokesperson says.

In addition to achieving meaningful capture rates, using CCS as a climate solution means operators also need to find secure locations to keep all the captured carbon stored for at least hundreds of years.

Grant Hauber, a strategic energy finance adviser with IEEFA, cited the Snohvit CCS project in Norway as an example of what can go wrong, even with careful preparation. SnohvitтАЩs original storage site, projected to have 18 yearsтАЩ worth of capacity, proved unusable after only 18 months, as CO2 was not being absorbed at the predicted rate, forcing operators to find alternative storage sites.

тАЬYou can have the best scientists in the world working on planning, but, in operations, they donтАЩt know how the CO2 will behave until they start putting it in the ground. ItтАЩs effectively a gamble,тАЭ Hauber says.

He adds that тАЬCO2 in the form itтАЩs injected underground … is highly corrosive,тАЭ noting that CO2-induced decay of well casings led to leaks at a seven-year-old CCS site in Illinois, leading to the suspension of operations in 2024.

Leaks can be dangerous. In 2020, 45 people in a Mississippi community were hospitalized when a CO2 pipeline ruptured; CO2 displaced the oxygen in the air and caused people to experience breathing difficulties тАФ some fell unconscious.

However, Zapantis emphasizes that, overall, CCS has an тАЬexcellent safety recordтАЭ across industryтАЩs тАЬmore than half a century of experience transporting very large quantities of CO2 via pipeline.тАЭ

Still, given the challenges and costs associated with CCS, there is a strong debate over just how widely it should be deployed.

Zapantis says he sees CCS having a role in decarbonizing JapanтАЩs heavy-emitting industries and fossil fuel-dependent power sector. Meanwhile, Hauber argues CCS should be limited to a small subset of industry where CO2 emissions are an unavoidable byproduct of chemical processes.

Climate advocates also question JapanтАЩs CCS plans.

тАЬCCS should certainly not be used in the power sector, where other options for decarbonization are available,тАЭ says FOEтАЩs Fukakusa.

тАЬNo matter what sector CCS is used in, the challenges of storing CO2 underground are the same,тАЭ she adds. тАЬThere still hasnтАЩt been sufficient assessment of which emission sources actually need CCS.тАЭ

тАШCarbon colonialismтАЩ

The four projects aiming to bury CO2 overseas are targeting sites in Malaysia, Indonesia and Australia. Oil and gas giants ExxonMobil and Petronas are among those involved.

The CO2 captured in Japan would need to be transported via a fleet of specialized ships, which are still being developed and tested. Domestic testing using a single vessel began late last year as part of the Tomakomai project.

A hot steel slab moves along a conveyor at a Nippon Steel plant in Kashima, Ibaraki Prefecture. The industry ministry positions says carbon capture and storage should be тАЬfully utilizedтАЭ in high-emitting sectors like steel and chemical manufacturing.

A hot steel slab moves along a conveyor at a Nippon Steel plant in Kashima, Ibaraki Prefecture. The industry ministry positions says carbon capture and storage should be тАЬfully utilizedтАЭ in high-emitting sectors like steel and chemical manufacturing.
| Bloomberg

Although exporting carbon is new territory for Japan, Nambo and Zapantis note that the proposed cross-border projects are straight from the government and industryтАЩs playbook, involving long-term investment in and relationships with overseas partners to ensure multiple sources of a given resource.

тАЬJOGMEC has supported Japanese private companies to secure equity for energy development, including oil, gas, coal and mineral resources overseas,тАЭ Nambo says, adding that this is how they are now approaching CO2 storage sites.

Many of the cross-border projects plan to use depleted offshore oil and gas fields as storage sites. Although JOGMEC says that CO2 from the exploratory projects wonтАЩt be used for extracting more fossil fuels, IEEFAтАЩs Hauber still cautions that тАЬhighly perforatedтАЭ former extraction sites may not be ideal storage locations.

тАЬThere are a lot of potential exit paths to be identified and managed,тАЭ he says. тАЬEven if locations of well perforations are known, if inferior materials were used or improperly installed, a leakage situation like that experienced in Illinois could eventually arise.тАЭ

If a leak should occur at an overseas storage site, тАЬit will be necessary to take measures in accordance with the CCS-related laws and regulations of the country concerned,тАЭ JOGMEC says.

In May 2024, 90 civil society organizations тАФ including 43 from Malaysia, Indonesia, Australia and Japan тАФ sent an open letter to the Japanese government asking it to halt its carbon export plans.

тАЬThis is nothing but carbon colonialism,тАЭ Fanny Tri Jambore of the nonprofit WALHI Indonesia wrote in a press release accompanying the letter.

While the JOGMEC-supported projects will give the government and industry more data to help determine how to invest in CCS going forward, Fukakusa worries that the technology is being prioritized ahead of proven, cost-competitive solutions.

тАЬThe biggest problem is that Japan has no policy to phase out fossil fuels such as coal, natural gas and oil,тАЭ she says. тАЬGovernment and industry emphasize CCS and assume it will be used.тАЭ

Leave a Reply